SCOPE
Engaged by Schneider Solar as their CSP, AULDEC provided their Services of Project Management for the execution of the 32 Inverter Stations installed onsite.
The scope included all interconnections between Inverter A & B, final commissioning, testing the entire HV & LV system, and then connecting the HV terminations.
The immense difficulties of completing this scope in Queensland’s notorious wet conditions created challenges for AULDEC. Still, the team could overcome any challenge to ensure that this project was completed to the highest level of quality to ensure its full operational status within the scheduled time frame.