SCOPE
Engaged by Schneider Solar as their CSP, Auldec provided their Services of Project Management and skilled labour resources for the execution of the 27 Inverter Stations installed onsite.
The scope included installing the 2-part skid into its final position and completing all interconnections between Inverter A & B, final commissioning, testing the entire HV & LV system, and then the connection of the HV terminations. With our specialised internationally trained inverter technicians, complete the final stages of energisation of the systems with the Schneider Engineers.
During Auldec commissioning efforts, they identified a design issue within the transformers and was engaged by Schneider to rectify this item. This was all still completed within the original schedule for this project, giving Auldec the reputation of the highest level of Quality Assurance and the ability to be reactive to solve and repair complex issues.