Ross River Solar Farm | TX Upgrade Project

RRSF_crane
SCOPE

 

AULDEC can provide its services anywhere in Australia, even under complex constraints, and this project did just that!

Engaged by Schneider Electric Solar, Auldec provided Project Management and experience in the change out of all 52 transformers on-site; the scope included all site logistics and cranage interfacing within a tight outage schedule provided to minimise production loss. Not only did Auldec provide and complete all these works within its schedule, but we also completed Inverter repairs during the outage of every solar skid to ensure the best resolution to reduce outage durations for both Schneider and Downer.

Auldec prides itself on building client satisfaction for every project. They believe that their forward-thinking and flexibility allowed for another well-executed project at the Ross River Solar Farm.

Auldec completed these works within the heavy constraints of Covid-19, and was still able to provide the service and safety our clients expect.

Client:
Schneider Electric Solar
Owner:
Downer
Location:
Townsville, QLD
Date:
April 2020 – August 2020

Copyright © 2025 AULDEC Solutions Pty Ltd.
All rights reserved.

EC010923

Copyright © 2024 AULDEC Solutions Pty Ltd.
All rights reserved.