SCOPE
The Wheatstone Project “Upstream Scope” included 60t of Busduct and installation and testing of MV/LV Switchgear. This was all completed on the 225m tall offshore facility during its fabrication in South Korea. This platform was then transported to Australia to supply dehydrated gas and dewatered condensate to the onshore facilities at Ashburton North.
The “Downstream Scope” of the Wheatstone Project delivered the 14 onshore LNG and domestic gas SWRMs at AMC site Henderson. Auldec then were involved with completion at the Onslow site location where we completed and final.
Auldec was instrumental in constructing, commissioning, and delivering some of the largest switch-rooms ever constructed. Our commitment, expertise and flexibility ensured Auldec met the project on time and schedule. All works carried out were completed with ZERO injuries.